Sequence of Jobs which Minimizes Completion Time for All Jobs

Question

Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Sigma before work center Delta. According to Johnson's rule, what sequence of jobs will minimize the completion time for all jobs?

Please show all your work and provide the GANT chart.

Job

Sigma

Delta

R

40

10

S

25

30

T

50

20

U

35

35

V

55

15

Summary

This question belongs to operations management and discusses about Johnson’s rule on sequence of jobs.

Word count: NA

 

Download Full Solution

Comments

  • HWA
    Rasha

    this is a very good website

  • HWA
    maani

    I have 50 questions for the same test your page is showing only 28

  • HWA
    joeanne

    hi can you please help or guide me to answer my assignments. thanks

  • HWA
    joeanne

    hi can anyone help or guide me to my assignments. thanks

  • HWA
    Monik


  • HWA
    Cristina

    This solution is perfect ...thanks

  • HWA
    Janete

    Hello Allison,I love the 2nd image that you did! I also, had never heard of SumoPaint, is something that I will have to exolpre a bit! I understand completely the 52 (or so) youtube videos that you probably watched. Sometimes they have what you want, sometimes they don't! However, it is always satisfying when you are able to produce something that you have taught yourself. Great job!Debra 0 likes

  • HWA
    Sandeep

    Perfect bank of solution. 

  • HWA
    Oxana

    great !

  • HWA
    Paul Brandon-Fritzius

    thanks for the quick response. the solution looks good. :)

  • HWA
    tina Johnson

    thnx for the answer. it was perfect. just the way i wanted it. 

  • HWA
    Giuseppe

    works fine.