Sequence of Jobs to be Ranked Based on Decision Rules

Question

The following jobs are waiting to be processed at the same machine center. Jobs are logged as they arrive:

Job

Due Date

Duration (days)

A

412

12

B

418

22

C

420

34

D

429

45

E

435

48

F

451

52

 

In what sequence would the jobs be ranked according to the following decision rules:

1. FCFS

2. EDD

3. SPT

4. LPT

All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 265. Which decision is best and why?

Summary

This question belongs to operations management and discusses about sequence of jobs to be ranked according to decision rules.

Word count: NA

 

Download Full Solution

Comments

  • HWA
    Rasha

    this is a very good website

  • HWA
    maani

    I have 50 questions for the same test your page is showing only 28

  • HWA
    joeanne

    hi can you please help or guide me to answer my assignments. thanks

  • HWA
    joeanne

    hi can anyone help or guide me to my assignments. thanks

  • HWA
    Monik


  • HWA
    Cristina

    This solution is perfect ...thanks

  • HWA
    Janete

    Hello Allison,I love the 2nd image that you did! I also, had never heard of SumoPaint, is something that I will have to exolpre a bit! I understand completely the 52 (or so) youtube videos that you probably watched. Sometimes they have what you want, sometimes they don't! However, it is always satisfying when you are able to produce something that you have taught yourself. Great job!Debra 0 likes

  • HWA
    Sandeep

    Perfect bank of solution. 

  • HWA
    Oxana

    great !

  • HWA
    Paul Brandon-Fritzius

    thanks for the quick response. the solution looks good. :)

  • HWA
    tina Johnson

    thnx for the answer. it was perfect. just the way i wanted it. 

  • HWA
    Giuseppe

    works fine.