Material Requirement and Planning for Given Data

Question

A manufacturing plant produces an end-item A, according to the following bill of materials:

The MPS for the end-item A is given in table 1. The manufacturing / assembly lead times, the lot sizing rules, and the current on-hand inventory for all constituting items are given in table 2. There are scheduled receipts for item C at week 1 (100 pieces) and for item D at week 3 (80 pieces).

Table 1: MPS Quantities

MPS Quantities

1

2

3

4

5

6

7

8

9

10

Gross Requirements (Α)

-

30

-

50

-

200

-

120

180

60

 

Table 2: Lead times, lot sizing rules, on-hand inventory

Item

Lead Time

Lot sizing rule

On-hand inventory

A

2 weeks

Lot-for-Lot

40

B

1 week

Lot-for-Lot

20

C

2 weeks

Lot-for-Lot

20

D

3 weeks

Lot-for-Lot

300

 

Determine the material requirement plan (fill the following tables).

 

Item: A

Production Lead Time: 2 weeks

Lot size rule:  Lot-for-Lot

Week No.

1

2

3

4

5

6

7

8

9

10

Gross Requirements

 

 

 

 

 

 

 

 

 

 

Adjusted Scheduled Receipts

 

 

 

 

 

 

 

 

 

 

Projected on-hand       40

 

 

 

 

 

 

 

 

 

 

Net Requirements

 

 

 

 

 

 

 

 

 

 

Planned order receipt

 

 

 

 

 

 

 

 

 

 

Planned order release

 

 

 

 

 

 

 

 

 

 

 

Item: B

Production Lead Time: 1 week

Lot size rule: Lot for Lot

Week No.

1

2

3

4

5

6

7

8

9

10

Gross Requirements

 

 

 

 

 

 

 

 

 

 

Adjusted Scheduled Receipts

 

 

 

 

 

 

 

 

 

 

Projected on-hand       20

 

 

 

 

 

 

 

 

 

 

Net Requirements

 

 

 

 

 

 

 

 

 

 

Planned order receipt

 

 

 

 

 

 

 

 

 

 

Planned order release

 

 

 

 

 

 

 

 

 

 

 

Item: C

Production Lead Time: 2 week

Lot size rule:  Lot-for-Lot

Week No.

1

2

3

4

5

6

7

8

9

10

Gross Requirements

 

 

 

 

 

 

 

 

 

 

Adjusted Scheduled Receipts

 

 

 

 

 

 

 

 

 

 

Projected on-hand     20

 

 

 

 

 

 

 

 

 

 

Net Requirements

 

 

 

 

 

 

 

 

 

 

Planned order receipt

 

 

 

 

 

 

 

 

 

 

Planned order release

 

 

 

 

 

 

 

 

 

 

 

Item: D

Production Lead Time: 3 weeks

Lot size rule: Lot for Lot

Week No.

1

2

3

4

5

6

7

8

9

10

Gross Requirements

 

 

 

 

 

 

 

 

 

 

Adjusted Scheduled Receipts

 

 

 

 

 

 

 

 

 

 

Projected on-hand     300

 

 

 

 

 

 

 

 

 

 

Net Requirements

 

 

 

 

 

 

 

 

 

 

Planned order receipt

 

 

 

 

 

 

 

 

 

 

Planned order release

 

 

 

 

 

 

 

 

 

 

Summary

This question belongs to operations management and discusses about material requirement and planning.

Word count: NA

 

Download Full Solution

Comments

  • HWA
    Rasha

    this is a very good website

  • HWA
    maani

    I have 50 questions for the same test your page is showing only 28

  • HWA
    joeanne

    hi can you please help or guide me to answer my assignments. thanks

  • HWA
    joeanne

    hi can anyone help or guide me to my assignments. thanks

  • HWA
    Monik


  • HWA
    Cristina

    This solution is perfect ...thanks

  • HWA
    Janete

    Hello Allison,I love the 2nd image that you did! I also, had never heard of SumoPaint, is something that I will have to exolpre a bit! I understand completely the 52 (or so) youtube videos that you probably watched. Sometimes they have what you want, sometimes they don't! However, it is always satisfying when you are able to produce something that you have taught yourself. Great job!Debra 0 likes

  • HWA
    Sandeep

    Perfect bank of solution. 

  • HWA
    Oxana

    great !

  • HWA
    Paul Brandon-Fritzius

    thanks for the quick response. the solution looks good. :)

  • HWA
    tina Johnson

    thnx for the answer. it was perfect. just the way i wanted it. 

  • HWA
    Giuseppe

    works fine.