Critical Path Activities And Their Time Variances

Question

Below is a table of activities required to finish a project:

Time estimate in days

Activity

Optimistic

Most Likely

Pessimistic

1

19

20

26

2

4

5

6

3

6

6

6

4

3

9

10


In calculating activity times for the project, which one of the following statements is correct?

A. Activity 1 will have the lowest variance

B. Activity 2 will have a variance of 0.11

C. Activity 3 will have the highest variance

D. Activity 4 will have a variance of 0.361

Summary

This multiple choice question belongs to Operations Management and it discusses about the activities and their variance in time estimate.

Total Word Count NA

Download Full Solution

Comments

  • HWA
    Rasha

    this is a very good website

  • HWA
    maani

    I have 50 questions for the same test your page is showing only 28

  • HWA
    joeanne

    hi can you please help or guide me to answer my assignments. thanks

  • HWA
    joeanne

    hi can anyone help or guide me to my assignments. thanks

  • HWA
    Monik


  • HWA
    Cristina

    This solution is perfect ...thanks

  • HWA
    Janete

    Hello Allison,I love the 2nd image that you did! I also, had never heard of SumoPaint, is something that I will have to exolpre a bit! I understand completely the 52 (or so) youtube videos that you probably watched. Sometimes they have what you want, sometimes they don't! However, it is always satisfying when you are able to produce something that you have taught yourself. Great job!Debra 0 likes

  • HWA
    Sandeep

    Perfect bank of solution. 

  • HWA
    Oxana

    great !

  • HWA
    Paul Brandon-Fritzius

    thanks for the quick response. the solution looks good. :)

  • HWA
    tina Johnson

    thnx for the answer. it was perfect. just the way i wanted it. 

  • HWA
    Giuseppe

    works fine.